Home Guides Topics About Compare

When Can a Victorian Building Contract Use Cost-Plus or Rise-and-Fall Terms?

·8 min read

Consumer Affairs Victoria’s Preparing a major domestic building contract guidance, dated 8 July 2025, identifies $1 million as the threshold above which cost-plus contracts are permitted and says a cost-plus method must not be used below $1 million. It permits a cost escalation or “rise and fall” clause only when the contract price is more than $500,000 and the Director of Consumer Affairs Victoria has approved the clause. The guidance says the Director had not approved any cost escalation clauses; figures checked 1 October 2026.

How do the two price thresholds differ?

The tests apply to different pricing methods and must be considered separately.

Pricing termPrice threshold in the Victorian guidanceAdditional requirement
Cost-plusMust not be used below $1 million. The guidance describes $1 million as the threshold above which cost-plus contracts are permitted.Consumer Affairs Victoria gives a narrow use for investigative work during an existing-house renovation.
Cost escalation or “rise and fall”Permitted only when the contract price is more than $500,000.The Director of Consumer Affairs Victoria must approve the clause. The reviewed guidance reports no approved cost escalation clauses.

A contract price over $500,000 does not remove the separate cost-plus prohibition below $1 million. Likewise, being over the rise-and-fall price threshold does not replace the requirement for Director approval.

What is the narrow cost-plus exception?

Consumer Affairs Victoria says a cost-plus contract can be used when renovating an existing house, but only to cover investigative work required to establish the contract price.

That arrangement must include:

Charging by the hour without a fixed contract price is the guidance’s example of a cost-plus method. The investigative exception does not allow the main renovation or all remaining work to continue on that basis.

Does a price over $500,000 automatically allow a rise-and-fall clause?

No. The contract price and Director approval are separate requirements. The price threshold is necessary but does not make the clause approved by itself.

The guidance reviewed for this article says the Director had not approved any cost escalation clauses. A builder should therefore check the Consumer Affairs Victoria page for any changed approval position before including a rise-and-fall clause, rather than relying on the price threshold alone.

Separately, the guidance says builders must calculate into the contract price any likely rise in costs caused by inflation, wage increases and the like. That requirement still needs to be addressed when preparing the contract.

What should builders check before offering the contract?

Consumer Affairs Victoria identifies $10,000 as the threshold amount for a major domestic building contract. Before offering the contract, builders should check the following:

This is general information, not financial or legal advice. Check the Consumer Affairs Victoria regulator page for the current contract rules and the relevant policy’s Product Disclosure Statement for insurance terms.

Sources

FAQ

What is a cost-plus method?

Consumer Affairs Victoria gives charging by the hour without a fixed contract price as an example. A cost-plus method must not be used for a contract below $1 million, apart from the narrow investigative-work situation described above.

Can cost-plus cover an existing-house renovation?

Only the investigative work needed to establish the contract price. The builder must provide a fair and reasonable estimate and then enter into a fixed-price contract for the remaining work.

Is a contract price over $500,000 enough to include a rise-and-fall clause?

No. The contract price must be more than $500,000, and the Director of Consumer Affairs Victoria must approve the clause. The reviewed guidance reports that no cost escalation clauses had been approved.

Should a builder rely on these thresholds when signing a contract?

No. Check the current Consumer Affairs Victoria regulator page and obtain appropriate legal advice if the contract structure is unclear. For insurance requirements, check the relevant policy’s PDS as well.

Quote